国产精品婷婷午夜在线观看 _国产精品亚洲自拍_天天综合日日夜夜精品 _蜜桃免费网站一区二区三区_都市激情国产精品_亚洲国产精品一区二区第四页av _heyzo一区

導航:全球石油化工網 >> 資訊頻道 >> 技術裝備

針對氣藏開發的多分支井技術(英)

[加入收藏][字號: ] [時間:2009-09-28 E&P 關注度:0]
摘要:簡介:多分支井技術,對于氣藏開發來說,具有非常有價值的作用。多分支井完井能夠保證長期的產能增量。 This multilateral completion uses five-stage openhole packer syste...
簡介:多分支井技術,對于氣藏開發來說,具有非常有價值的作用。多分支井完井能夠保證長期的產能增量。


This multilateral completion uses five-stage openhole packer systems.
Although multilateral (ML) well technology is often thought of as a tool primarily for offshore use to capture outlying pockets of hydrocarbons, the majority of the installations have actually been on land in low-cost environments. Applying this technology has shown many benefits, but only in a few cases is ML technology used as the main field development technique. However, as operators look at lowering field development costs while increasing production, they are turning to ML wells as the solution.

ML completions provide excellent opportunities in unconventional gas developments. Two or more laterals off of a single vertical well bore can result in considerable cost savings and increased production. However, for maximum benefits, production from two or more laterals has to match or exceed the rates expected of the same number of vertical wells. And the design has to incorporate the ability to selectively re-enter and stimulate stages in each wellbore in order to enhance overall hydrocarbon recovery.

In April 2000, Baker Hughes deployed the first Level 6 ML stackable splitter system designed for fracturing gas wells. This system had 5.5-in. tubing/casing looking up with two 5.5-in. legs looking down. In this application, two of these systems were stacked so that there were three lateral well bores. To run into the well, it had to drift through 133⁄8-in. casing and be cemented in 121⁄4-in. open hole. It provided selective access and selective stimulation to all laterals up to 7,500 psi pressure differentials. At the time, the procedure lacked the commercial viability to become a mainstream field development technique; however, multilateral technology has continued to advance so that simple and reliable high-pressure junctions can now be applied in low-cost environments.

Recently, an operator of an unconventional gas play put the technology to the test. The challenges for the ML wells in the Granite Wash reservoir in the Texas Panhandle were:
• Full opening 41⁄2-in., 3.875-in. drift production in both laterals;
• Sealed isolated junction that could withstand 10,000-psi fracturing treatments (TAML level 4 junction);
• Mechanical integrity across the junction to support the formation;
• Capabilities for re-entry and restimulation of both laterals at a future date;
• Lower cost as compared to two single wells; and
• Positive production results.



The HOOK Hanger (in blue) is latched into the key seat of a window cut in the casing. (Figures courtesy of Baker Hughes)

Baker Oil Tools Frac-HOOK and Frac-Point systems were chosen for the task as these systems do not require many additional trips to install. The Frac-HOOK ML casing fracturing system comprises a HOOK Hanger ML junction that provides mechanical support at the junction window and re-entry capabilities to all laterals. It has an extensive history of being used in TAML Level 3-5 completions at inclinations ranging from 0° to 90° and at junction depths at more than 14,000 ft (4,270 m). To obtain a high-pressure seal at the junction, a ZXP liner top packer is used as an integral part of the HOOK Hanger. Lateral and mainbore diverters are used to selectively fracture the formation as well as for future re-entry capabilities.

The system provides for one-trip deployment: The HOOK Hanger, with a lateral drilling diverter or lateral re-entry diverter pre-installed, is run as part of the lateral liner installation. Either of these diverters allows setting of bridge plugs and for perforating and fracing below the hanger in the lateral while maintaining pressure integrity across the hanger window. The mainbore fracing diverter allows similar functionality, but for the main bore. These diverters can be deployed with threaded pipe, coiled tubing, or a snubbing unit.

The Frac-Point system (liner top packer, openhole packers, frac sleeves, wellbore isolation valve, and pressure-actuated sleeves) allows completion of the well without cementing and perforating in the producing interval. Openhole packers provide isolation along the length of the liner, eliminating the need to cement the liner in the lateral section and increasing formation interface. They also eliminate the need for perforating because sleeves provide access to the zone of completion for both fracturing and production. Fracture treatments for each section can be pumped on the same day, eliminating the expense of mobilization and demobilization of pumping equipment. The system provides better fracture extension control than nonselective hydraulic fracturing, resulting in improved initial productivity and accelerated reservoir drainage.


The basic installation process for the well was:
• Drill main bore;
• Run Frac Point completion system in the mainbore lateral;
• Set whipstock above the lower completion, sidetrack the well, and drill the upper lateral;
• Retrieve whipstock from the well;
• Make up the upper system below the HOOK Hanger and run everything into the well, landing the hanger in the window;
• Fracture the lower lateral;
• Fracture the upper lateral; and
• Achieve commingled flow.

The design for the openhole packer system would use the following sizing:

Use Hole Size Casing Size To 12,000 ft (3,660 m) 97⁄8 in. 75⁄8 in.

In laterals 61⁄8 in. 41⁄2 in.

This particular well was drilled on a pad that also had an offsetting single-lateral well that needed stimulation. Therefore, the plan was to stimulate the bottom lateral of the ML and then rig over and stimulate the single-lateral well. While that well was being treated, the diverters on the ML were switched simultaneously. Once the single-lateral offset well was completed, the pumping crews would switch back to treat the upper lateral of the ML. This saved the operator mobilizing charges for the pumping crews and maximized potential savings on all three laterals, which were stimulated in the course of one week. Both laterals were completed using five-stage openhole packer systems (Figure 1). Both laterals are now open and producing.

Results

The hanger system delivered two installed, stimulated, and producing laterals. The Frac-Point systems were run to total depth, and pressure integrity was maintained during all stimulation operations. The production results from the well met or exceeded expected results from offsetting wells. The cost savings were realized over drilling and completing two separate wells. The drilling cost proved to be 15% to 20% less, and the completion costs were nearly 50% cheaper than the average for stimulating two separate laterals. This reflects the cost savings captured by performing consecutive pumping operations on the pad without mobilizing and demobilizing pumping crews.

This well demonstrates the strong economic potential of ML completions in unconventional gas developments. Operators can save capital investment by accessing production from two laterals while drilling a single vertical well bore. Greater drainage access across a section is also possible by using this technology.

Maximizing production in the future

Hydraulically fractured ML gas wells have gained significant acceptance in the North American market, and the technology is moving into the international arena.

Baker Hughes completed a similar installation technique in Africa recently. The expected production result was 15 Mcf/d, but the production came in at 85 Mcf/d.

Although these results are not typical, it should not take long to gain acceptance on a global scale if success stories yield a five-times-greater production increase.

Currently, a North American gas well using two HOOK Hanger systems with three lateral legs is being completed and should realize an additional 15% to 20% savings over a single Hook Hanger deployment. Depending on the reservoir, as more lateral legs are added, the hydrocarbon recoverable factor significantly increases due to maximum reservoir exposure and more efficient well spacing and subsequent drainage.

Baker’s current pressure limit for ML equipment used in well fracturing is 10,000 psi. The future will easily push this limit, with formations being evaluated where the application of this technology could be 12,500 psi and possibly even 15,000 psi differentials.

Reservoir prediction models will have to be honed and improved to stay up with the results seen in the field. Well monitoring and intelligent production systems will begin to play a significant roll in multilateral completion techniques to maximize production, improve models to better understand reservoir drainage, and to minimize water production. 

楊寶劍 是振威(全球)石油網的高級技術編輯,在石油技術資訊行業有八年的學識和經驗。他源源不斷地提供石油行業全球最新的技術創新、研發成果、現場應用情況等信息。如果你對“新技術新產品”的內容有任何問題或建議,請聯系楊寶劍編輯 +86 10-58236512 Email:allenyo@zhenweiexpo.com 歡迎您提供手中的最新技術文章!
關鍵字: 多分支井 
關于我們 | 會員服務 | 電子樣本 | 郵件營銷 | 網站地圖 | 誠聘英才 | 意見反饋
Copyright @ 2011 m.1314163.com Inc All Rights Reserved 全球石油化工網 版權所有 京ICP證080561號
国产精品婷婷午夜在线观看 _国产精品亚洲自拍_天天综合日日夜夜精品 _蜜桃免费网站一区二区三区_都市激情国产精品_亚洲国产精品一区二区第四页av _heyzo一区
奇米一区二区三区| 成人免费一区二区三区视频 | 久久久噜噜噜久久中文字幕色伊伊| 91丨porny丨中文| 国产盗摄一区二区| 激情久久五月天| 精品在线亚洲视频| 男男成人高潮片免费网站| 亚洲bt欧美bt精品777| 一区二区三区四区中文字幕| 国产精品日韩精品欧美在线| 国产午夜精品美女毛片视频| 国产欧美日韩久久| 亚洲精品欧美综合四区| 夜夜精品浪潮av一区二区三区| 亚洲精品视频免费观看| 亚洲高清不卡在线观看| 秋霞成人午夜伦在线观看| 免费成人av在线播放| 国产一区二区精品在线观看| 成人免费观看男女羞羞视频| 色吊一区二区三区| 日韩一级二级三级精品视频| 国产日韩欧美高清在线| 亚洲三级免费观看| 日韩精品乱码av一区二区| 国产一区二区三区四| 国产91精品露脸国语对白| 日本久久电影网| 欧美va日韩va| 亚洲天天做日日做天天谢日日欢 | 处破女av一区二区| 在线观看亚洲一区| 国产午夜三级一区二区三| 久久草av在线| 欧美色偷偷大香| 欧美极品aⅴ影院| 午夜视黄欧洲亚洲| 97se亚洲国产综合自在线观| 欧美大片一区二区| 国产精品久久久久精k8| 免费av成人在线| 91蜜桃网址入口| 亚洲少妇中出一区| 99久久免费精品高清特色大片| 日韩情涩欧美日韩视频| 亚洲国产精品久久人人爱蜜臀 | 麻豆精品国产传媒mv男同| 成人蜜臀av电影| 国产精品你懂的| 大尺度一区二区| 久久婷婷国产综合国色天香| 精品亚洲porn| 久久久国产一区二区三区四区小说| 青青草国产成人99久久| 日韩一区二区三区视频在线观看| 天天色天天爱天天射综合| 欧美精品 国产精品| 波多野结衣在线一区| 亚洲国产成人一区二区三区| 精品一二三四在线| 久久久久久免费| av亚洲精华国产精华| 国产精品国产三级国产普通话99 | 久久精品国产久精国产| 91麻豆精品国产91久久久资源速度| 香港成人在线视频| 欧美一级夜夜爽| 国产一区二区在线影院| 欧美国产成人在线| 欧洲亚洲精品在线| 久久se这里有精品| 亚洲视频综合在线| 日韩三级视频在线看| 国产不卡一区视频| 亚洲国产综合视频在线观看| 国产日产欧美一区| 在线观看网站黄不卡| 国产精品资源网| 亚洲午夜羞羞片| 欧美国产日韩精品免费观看| 一本一道久久a久久精品 | 国产一区高清在线| 亚洲一区视频在线| 中文字幕五月欧美| 日韩欧美成人一区| 欧美日韩精品系列| 99精品欧美一区二区蜜桃免费| 日本欧美大码aⅴ在线播放| 亚洲欧美一区二区三区久本道91 | 懂色av一区二区夜夜嗨| 三级欧美在线一区| 亚洲一区日韩精品中文字幕| 国产精品另类一区| 精品国产亚洲在线| 欧美一区二区三区在线观看视频| 色哟哟亚洲精品| 一本色道久久综合亚洲91| 成人免费毛片a| 5858s免费视频成人| 欧美日韩免费视频| 91老司机福利 在线| 不卡视频免费播放| 成人一区二区在线观看| 成人免费视频一区二区| 成人av网站免费| 色综合天天性综合| 国产成人精品亚洲午夜麻豆| 国产成人自拍高清视频在线免费播放| 免费av成人在线| 国产精品一区三区| 99国产精品一区| 欧美日韩精品一区二区在线播放| 在线中文字幕一区| 67194成人在线观看| 日韩精品一区二区在线观看| 亚洲精品一区二区三区福利| 精品少妇一区二区三区视频免付费 | 99久久免费精品高清特色大片| 成人综合激情网| 99久久国产综合精品色伊| 欧美日韩一区不卡| 91精品国产入口| 中文字幕av不卡| 亚洲成人av中文| 国模娜娜一区二区三区| 99视频一区二区三区| 欧美日精品一区视频| 精品理论电影在线| 亚洲另类中文字| 另类欧美日韩国产在线| 波多野结衣中文字幕一区二区三区| 欧美日韩aaaaa| 国产精品素人一区二区| 日韩高清在线不卡| 色悠久久久久综合欧美99| 26uuu欧美日本| 琪琪一区二区三区| 欧美人与禽zozo性伦| 亚洲免费观看高清完整版在线观看熊| 国产一区二区三区在线观看精品| 91成人免费网站| 亚洲婷婷在线视频| 91在线免费视频观看| 精品国产1区2区3区| 日韩制服丝袜先锋影音| 色综合久久久久| 亚洲精品国产无套在线观| 成人sese在线| 亚洲精品美国一| 欧美亚洲综合另类| 一区二区在线观看免费| 色94色欧美sute亚洲线路一ni | 国产拍揄自揄精品视频麻豆| 久久精品久久99精品久久| 精品少妇一区二区三区免费观看| 亚洲第一成人在线| 3atv一区二区三区| 蜜臀av在线播放一区二区三区 | 中文字幕中文字幕一区二区 | 亚洲日本韩国一区| 日本精品裸体写真集在线观看| 亚洲午夜国产一区99re久久| 欧洲生活片亚洲生活在线观看| 婷婷成人综合网| 国产色综合久久| 91小宝寻花一区二区三区| 精品国产亚洲在线| 欧美综合天天夜夜久久| 日韩福利电影在线| 欧美激情综合五月色丁香| 91网站最新地址| 奇米色777欧美一区二区| 国产欧美综合在线观看第十页| 在线一区二区三区| 黄色精品一二区| 国产精品护士白丝一区av| 欧美丰满一区二区免费视频| 国产精品自在欧美一区| 午夜激情久久久| 亚洲欧美一区二区三区孕妇| 日韩欧美中文字幕制服| 91丝袜高跟美女视频| 开心九九激情九九欧美日韩精美视频电影| 中文字幕国产一区二区| 日韩精品在线看片z| 欧美色成人综合| 色综合久久久久网| www.日本不卡| 91在线免费视频观看| 中文字幕在线观看一区| 精品乱码亚洲一区二区不卡| 欧美高清视频一二三区| 91麻豆国产精品久久| 午夜不卡在线视频| 一区二区成人在线观看| 久久久.com| 中文字幕五月欧美| 亚洲欧洲成人av每日更新| 国产精品久久久久影院亚瑟 |